Question: Multiple critical paths can exist under CPM because: Question 11Select one: a. There is more than one way to complete the project b. Different network
Multiple critical paths can exist under CPM because: Question 11Select one: a. There is more than one way to complete the project b. Different network paths exist, each with the same total time c. Great flexibility of activity sequences is available d. None of the above
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
