Question: Multiple critical paths can exist under CPM because: Question 11Select one: a. There is more than one way to complete the project b. Different network

Multiple critical paths can exist under CPM because: Question 11Select one: a. There is more than one way to complete the project b. Different network paths exist, each with the same total time c. Great flexibility of activity sequences is available d. None of the above