Question: Must Show All work !!!!!!!!!!!!!!!!!!!!!!!!!!! Please show all work!! . The following information relates to a project (task times are in weeks): Task Preceding Tasks

Must Show All work !!!!!!!!!!!!!!!!!!!!!!!!!!!

Must Show All work !!!!!!!!!!!!!!!!!!!!!!!!!!!

Please show all work!!

. The following information relates to a project (task times are in weeks): Task Preceding Tasks to tm A None 8 9 10 B None LO 9 12 A 3 5 7 D B 8 14 19 E CD 7 12 16 TI F E 10 14 18 G F 6 10 15 What is the probability that the project can be completed within 60 weeks? What is the probability that the project will take longer than 60 weeks