Question: MUST show Excel calculation for payback Expected Net Cash Flows Time Project A Project B 0 ($375) ($575) 1 ($300) $190 2 ($200) $190 3

MUST show Excel calculation for payback

Expected Net Cash Flows
Time Project A Project B
0 ($375) ($575)
1 ($300) $190
2 ($200) $190
3 ($100) $190
4 $600 $190
5 $600 $190
6 $926 $190
7 ($200) $0
f. What is the regular payback period for these two projects?
Project A
Time period 0 1 2 3 4 5 6 7
Cash flow (375) (300) (200) (100) 600 600 926 (200)
Cumulative cash flow -$375 -$675 -$875 -$975 -$375 $225 $1,151 $951
Intermediate calculation for payback
Payback using intermediate calculations 4.625