Question: My software development company has the databases, tools, and staff to design up to 24 programs per week with an effective capacity of 17 programs
My software development company has the databases, tools, and staff to design up to 24 programs per week with an effective capacity of 17 programs per week.
What is its efficiency if it designs an average of 15 programs per week? (Your answer should be a percentage with one decimal point.)