Question: n a start - to - start relationship, a 2 - day lag implies that: a . The successor should not start until two days

n a start-to-start relationship, a 2-day lag implies that:
a.
The successor should not start until two days after the predecessor has started.
b.
The two activities can start on the same date.
c.
The successor should not start until two days after the predecessor has been completed.
d.
There is a mandatory dependency between the two activities