Question: n performing bottom-up estimating, you take each activity in a work package and, in calculating the costs for that activity, take into considering which two
n performing bottom-up estimating, you take each activity in a work package and, in calculating the costs for that activity, take into considering which two of the following? (select all that apply)
| A. | Work effort | |
| B. | Materials required | |
| C. |
Hourly or daily rate | |
| D. |
Breaks, sick-leave, vacation and holiday time |
| A. | Identification | |
| B. | Segmentation | |
| C. | Analysis | |
| D. | Probability | |
| E. | Impact | |
| F. | Response |
Two of the outcomes of risk planning are: (select two responses)
| A. | Risk acceptance criteria | |
| B. | Risk probability and impact matrix | |
| C. | Risk register | |
| D. | Risk log |