Question: Name: ID: d . An order for 7 5 units is processed through work centers x and Y . The setup time on x is

Name:
ID:
d. An order for 75 units is processed through work centers x and Y. The setup time on x is 40 minutes, and the run time is 5 minutes per piece. The setup time on Y is 25 minutes, and the run time is 2.5 minutes per piece. The wait time between the two operations is 8 hours. The move time between x and Y is 60 minutes. After operation Y, there is a wait time of 4 hours before moving into storage, and the move time into storage is 2 hours. Calculate the total manufacturing lead time for the order. (1.5 marks)