Question: Name: ( LO 5 & LO 6 ) For the activities and the dependenceies shown below, do the following: a ) For the information given
Name:
LO & LO For the activities and the dependenceies shown below, do the following:
a For the information given below draw the network diagram using Activity on Arrow method.
b Calculate the earliest and latest event times.
c Show the critical path on the network.
tableActivitytableImmediatePredecessorstableEstimatedDurationA monthBA monthsCB monthsDB monthsEB monthsFC monthsGDE monthsHF monthGH months monthsK monthsL monthsMK monthsNL months