Question: Name uID U Problem Set 4 - Note: You will find the Example videos in the module very helpful in answering these questions. Please type

Name
uID
U
Problem Set 4
-Note: You will find the Example videos in the module very helpful in answering these questions.
Please type in the space provided.
Question 1. An assembly line with 8 tasks is to be balanced. The longest task is 12 minutes,
and the total time for all tasks is 48 minutes. The line will operate for 480 minutes per day.
Round up your answers to the nearest whole number (40 points, 10 points each). See
Lecture M4-2 for details.
Question 2. A manager wants to assign tasks to workstations as efficiently as possible. Part A:
Using the following precedence diagram to complete the table with # of following task,
positional weight for nodes g,h and i and Time (Time is in minutes).(Part A: 45 points, 5 points
each)
B. What is the total time for all tasks? (5 points)
C. If the line operates 480 minutes a day, what is the maximum output, round your answer
down to the nearest whole number. (10 points)?
 Name uID U Problem Set 4 -Note: You will find the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!