Question: NEC 4 ECC - A month before the defects date, the Supervisor carries out an inspection of the school and observes that there is some

NEC4 ECC -
A month before the defects date, the Supervisor carries out an inspection of the school and observes that there is some flooding in parts of the car park. The finished levels of the car park do not comply with the Scope, this is causing the flooding and accordingly the Supervisor notifies the matter as a Defect. The Client does not allow the Contractor access to the car park to correct the Defect. When the Supervisor issues the Defects Certificate, the Supervisor includes a statement that the notified Defect has not been corrected.
Which of the following statements best describes how the Project Manager assesses the final amount due in respect of the uncorrected Defect?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!