Question: NEC 4 If the Project Manager has given an instruction to the Contractor which removes work from the Scope, which ONE of the following statements
NEC If the Project Manager has given an instruction to the Contractor which removes work from the Scope, which ONE of the following statements best represents the actions required by the Project Manager?
Select ONE option
Notify the Contractor of a compensation event at the same time as giving the instruction to remove the work and include an instruction to submit a quotation for reduced Prices and an earlier Completion Date
Notify the Contractor of a compensation event and include an instruction to submit a quotation for reduced Prices and an earlier date for planned Completion
Notify the Contractor of a compensation event, issue an early warning and instruct the submission of a revised programme
Notify the Contractor of a compensation event at the same time as giving the instruction to remove the work and include an instruction to submit a quotation for the event in the notification
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!