Question: Need: ES, EF, LS, LF Slack: Critical path: Total Completion time: Dave Fletcher was able to determine the activity times for constructing his laser scanning

Need: ES, EF, LS, LF
Slack:
Critical path:
Total Completion time:
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: \begin{tabular}{ccc|ccc} \hline \multicolumn{2}{r|}{ Activity } & Time (weeks) Immediate Predecessor(s) & \multicolumn{2}{c}{ Activity } & Time (weeks) Immediate Predecessor(s) \\ \hline A & 5 & - & E & 5 & B \\ B & 8 & - & F & 6 & B \\ C & 3 & A & G & 9 & C,E \\ D & 3 & A & H & 6 & D,F \\ \hline \end{tabular}