Question: Please help me to identify each activities ES, EF, LS, LF, Slack, and Critical activity. THX!!! Dave Fletcher was able to determine the activity times

Please help me to identify each activities ES, EF, LS, LF, Slack, and Critical activity. THX!!!Please help me to identify each activities ES,

Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Time Immediate Time Activity (weeks) Predecessor(s) Activity (weeks) A 6 E 4 B 7 F 6 3 A G 11 D 3 A H 8 Immediate Predecessor(s) B B CE DF