Question: need fast stright answer without explination Question 31 2.5 pts Suppose you are managing a product development project. The project is expected to be completed

need fast stright answer without explination need fast stright answer without explination

Question 31 2.5 pts Suppose you are managing a product development project. The project is expected to be completed in 10 months. The budgeted cost of the project is 100,000. After 1 month, you realize that the project is 10 percent completed at a total expense of 25,000. The planned completion should have been 20% at this point. What is the Schedule Variance? O 5,000. 25,000. 0-25,000. O None of the answers. 0-10,000