Question: NEED HELP CRITIRCAL QUESTION 1 HOUR DEADLINE QUICK SOLUTIN PLEASE HELP Question 3. (30 points) Given the following project: Activity Predecessor Normal Time (day) Normal

NEED HELP CRITIRCAL QUESTION 1 HOUR DEADLINE QUICK SOLUTIN PLEASE HELP

NEED HELP CRITIRCAL QUESTION 1 HOUR DEADLINENEED HELP CRITIRCAL QUESTION 1 HOUR DEADLINENEED HELP CRITIRCAL QUESTION 1 HOUR DEADLINENEED HELP CRITIRCAL QUESTION 1 HOUR DEADLINE

Question 3. (30 points) Given the following project: Activity Predecessor Normal Time (day) Normal Cost ($) Crash Time (day) Crash Cost ($) A 5 40 5 40 B 5 30 5 30 10 40 5 70 D B 7 40 2 60 E 6 30 2 50 F CD 11 60 5 90 G C,D 6 30 4 60 H E,F 5 20 1 32 G 4 20 4 20 Note: A,B and I not crashable. (a) (9 Points) Draw the network and find the critical path duration of the project, total cost of project using normal times. . (b) (4 Points) Calculate the maximum time reduction and crash cost-per-day (all activities may be partially crashed) for each activity. Then fill the table below. Activity Maximum Time Reduction (day) Cost to Crash per Period ($/day) A B D E F G H - (c) (9 Points) Calculate the cost of the project at each iteration (or step) until you can no longer crash the project any further. Continue crashing until you can't crash any more. Project Duration (day) Total Direct Costs Normal duration 1st iteration 2nd iteration 3rd iteration 4th iteration 5th iteration (d) (8 Points) Assume each day the project incurs an indirect cost of 7$. Based on the calculations you made on part (c), what would be the optimal duration with lowest cost including the indirect costs. Project Duration (copy from part (c)) Total Direct Costs (copy from part (c)) Indirect costs TOTAL COST Normal duration 1st iteration 2nd iteration 3rd iteration 4th iteration 5th iteration

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!