Question: need help with 7 and 8 please 7. Given the following MRP tableau, what is the order quantity needed to meet the demand for week

need help with 7 and 8 please need help with 7 and 8 please 7. Given the
7. Given the following MRP tableau, what is the order quantity needed to meet the demand for week 6? And when should it be placed? Lead Time = 3 weeks 1 2 3 4 5 6 MPS 200 250 100 600 4501000 Orders Due In Orders placed On Hand Quantity = 600 1 8. Given the following MRP tableau, what is the order quantity needed to meet the demand for week 62 And when should it be placed? Lead Time = 3 weeks; Lot size = 400 2 3 4 5 6 MPS 200 250 100 600 450 1000 Orders Due In Orders Placed On Hand Quantity = 600