1. Based on the following AOA diagram, please answer the following question: (1) Determine the critical path and the expected project duration (2) Determine the following quantities for each activity: the earliest start time, the latest start time, the earliest finish time and the latest finish time and the slack time. C (7) F (5) 1 (6) A (4) T B (10) 2 D (11) m 5 E (12) G (3) H (10) I 00