Question: Need the early start & finish time, late start and finish time, activity slack, critical path for this. A group of developers is building a

Need the early start & finish time, late startNeed the early start & finish time, late start and finish time, activity slack, critical path for this.

A group of developers is building a new shopping center. A consultant for the developers has developed the following table of activities, durations and predecessors. Determine the earliest start times and finish times, latest start and finish times, activity slack, critical path and duration for the project. There is a Bonus for finishing the project at 90% of the projected date. The bonus for early completion is $50,000. Which activities should be crashed, if the cost for 1 week reduction, for any activity, is $3500 per week, and what is the total cost of crashing? And, Net Bonus, if any. Predecessor Activity A Duration 1 B 8 C D 12 3 E F 9 3 G H 2 12 I J Description Award Kick-off Contract for Crew/Mach Purchase Material Excavation Build Foundation Electrical-Outside Paving Lighting - Exterior Electrical - Inside Bldg Construction Sewage System Parking Lots Final Wiring Plumbing Interior - Finish HVAC Landscape & Paint Furnish Completion - Keys A B, C, D D D E, F, G E, F E, F, G E, F, G H 1,J H, MN MN L O, P Q R 7 30 21 20 5 16 17 5 L M N O P Q 6 R 3 1 X

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!