Question: need to know the CPM since my calculation is wrong A contractor has secured a tender to build a small prayer house for Sekolah Siswa

need to know the CPM since my calculation is

need to know the CPM since my calculation is wrong

A contractor has secured a tender to build a small prayer house for Sekolah Siswa Bistari. He has listed the following activities for the project: Activity Preceding Activity(s) Duration (weeks). A 5 B 2 C A 8 D AB 1 E C.D 2 F 4 G D 3 H F 2 I E.F 7 J G 6 H. 4 a) Construct the CPM network for the project. (5 marks) b) Compute the Earliest Event Time and Latest Event Time for each event. (4 marks)