Question: Need to solve this question professionally ; Thanks Task Examine the following network diagram (duration in weeks) and answer the questions that follow: D=3 2
Need to solve this question professionally ; Thanks

Task Examine the following network diagram (duration in weeks) and answer the questions that follow: D=3 2 A=6 E=4 F=& J=6 1 B=4 K=7 6 8 C=3 H=8 L=6 4 1=5 Required: 1. Draw a new precedence (AON) network diagram and compute and indicate on the diagram Early Start, Early Finish, Late Start, and Late Finish times for each activity. (15 pts.) 2. Based on the diagram created in (1) above, compute (a) Free Slack and (b) Total Slack for each activity, and organize your answers on a table (12 prs.) 3. Based on your answers in (2) above, identify the activities that provide scheduling flexibility (3 prs.)