Question: Net Present Value (NPV) Project One Cash flow Discounted CF. Discount Rate NPV Method 1 Year 0 Year 1 Year 2 Year 3 Year 4

 Net Present Value (NPV) Project One Cash flow Discounted CF. Discount

Net Present Value (NPV) Project One Cash flow Discounted CF. Discount Rate NPV Method 1 Year 0 Year 1 Year 2 Year 3 Year 4 NPV -1000 500 400 300 100 -1000 454.55 330.58 225.39 68.30 10% NPV Method2 78.82 Year 2 Year 0 -1000 Year 1 100 Year 3 400 Year 4 500 300 Project Two Cash flow Discounted CF. Discount Rate NPV Method 1 NPV Method2 Year 2 Year 0 -2000 Year 1 500 Year 3 300 Year 4 750 500 Project Three Cash flow Discounted CF. Discount Rate NPV Method 1 8% NPV Method2