Question: Netflix has identified 7 key activities it must complete to release the newest season of one its most popular shows. Activity Duration in weeks Immediate
Netflix has identified 7 key activities it must complete to release the newest season of one its most popular shows. Activity Duration in weeks Immediate Predecessor(s) A 9 - B 4 A C 4 A D 6 A E 9 B, C F 6 C, D G 7 E, F Draw an Activity-on-Node Network to represent this project. Find the critical path. Complete a forward and backward pass to derive the earliest start (ES), earliest finish (EF), latest start (LS), latest finish (LF) and slack times for all of the activities. Calculate and enter the minimum project completion time. Enter your answers as an integer