Question: Network Diagram Question, thanks in advance! Can you please develop a network diagram, calculate critical path(how long this project will take), and assuming a July
Network Diagram Question, thanks in advance! Can you please develop a network diagram, calculate critical path(how long this project will take), and assuming a July 1st start date, can you prepare a Gantt chart?
| Task ID | Task | Immediate Predecessors | Duration (weeks) |
| A | Define concept and value proposition | 1 | |
| B | Identify & Collect Available Intellectual Property - Internal IP | A | 2 |
| C | Identify & Collect Available Intellectual Property - External IP | A | 2 |
| D | Inventory Relevant Stories/Cases | B,C | 1 |
| E | Identify/Schedule First-hand Interviews | D | 1 |
| F | Conduct Interviews | E | 2 |
| G | Develop Book Proposal | D | 1 |
| H | Develop Draft Version 0 | G | 3 |
| I | Solicit and Integrate Feedback | H | 2 |
| J | Revise & Refine concept/structure | I | 1 |
| K | Draft & revise Version 1-N | I,J | 8 |
| L | Develop Layout and Cover Design | J | 1 |
| M | Develop Marketing & Rollout Plan | G | 2 |
| N | Prepare Draft N for publication | K,L | 2 |
| O | Publish | M,N | 1 |
Step by Step Solution