Question: Network diagramming is a logical, sequential process that requires you to consider the order in which activities should occur to schedule projects as efficiently as

Network diagramming is a logical, sequential process that requires you to consider the order in which activities should occur to schedule projects as efficiently as possible. Remember that all projects have predecessors, or activities, that must/should occur before the next step within a project plan can take place. Using a project scheduling application, complete the following: Construct a linked bar-chart and an AON diagram for the schedule shown in Figure 6.4 of the textbook. Your schedule must include activity relationships, too. Please note that a Gantt chart that shows activity relationships is called a linked bar-chart.Network diagramming is a logical, sequential

158 SCHEDULE DEVELOPMENT 0 101 0 101 10 20 10 20 20 40 20 40 C, 10 e, 10 - f, 20 0 10 0 10 4050 40 50 50 50 50 50 a, o 9, 10 - h, o b,5 d, 15 0 5 5 10 10 25 25 40 Key Forward Pass: Left to Right Determine Early Start & Early Finish Activity Name Critical Path Early Start (ES) 20 46 a, Late Start (LS) 20 40 Early Finish (EF) Late Finish (LF) Activity Duration Backward Pass: Right to Left Determine Late Finish & Late Start Figure 6.4: Forward and Backward Pass

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!