Question: NETWORK: PERT Ex . 1 SPRING 2 4 - KEY Consider the following table: ACTIVITY A B C D E F G PREC. ACT. -

NETWORK: PERT Ex.1 SPRING 24- KEY Consider the following table:
ACTIVITY
A
B
C
D
E
F
G
PREC. ACT.
---
---
---
A
B
C
D, E, F
TIME ESTIMATES (days)
To
3
2
2
3
3
2
4
Tml
5
4
3
4
5
4
5
Tml
7
6
4
5
13
6
6
Te
5
4
3
4
6
4
5
\sigma
(6-2)/6=(2)/(3) TO 4/9
(13-3)/6=10/6 TO 25/9
(6-4)/6=(1)/(3) TO 1/9
1) Construct a PERT network.
3223324
5746
34
45
513
46
56
G (10,15)5(10,15)
5(4-2)/6=1/3
4(6-2)/6=2/34/9
3(6-2)/6=2/3
4(5-3)/6=1/3
6(13-3)/6=10/625/9
4(6-2)/6=2/3
5(6-4)/6=1/31/9
A (0,5)
5(1,6)
B (0,4)4(0,4)
C(0,3)3(3,6)
D (5,4(6,10)
E (4,10)6(4,10)
F (3,7)4(6,10)
9)
Te=1*t0.+4*tml +1*tp 6
*ExpectedTimes:Ate =5; Bte =4; Cte =3; Dte =4; Ete =6; Fte =4; Gte =52) By using ES, EF, LF, LS, find the slack of each activity and the critical path.
Slack = LF EF or LS ES Activity A: Slack =65=1 Activity B: Slack =44=0 Activity C: Slack =63=3 Activity D: Slack =109=1 Activity E: Slack =1010=0 Activity F: Slack =107=3 Activity G: Slack =1515=0
*The critical path would be Activity B, E, G. These activities must be fulfilled without delay, as shown by there being no slack or allowance associated with these activities.
3) Find the completion time and the standard deviation (\sigma ) for the project round off the standard deviation to the nearest hundredth: two decimal places.
\sigma =(tp to)/6 squared of squared SUM
B: (6-2)/6=2/3 squared4/9 OR 0.4444 E: (13-3)/6=10/6 squared100/36=25/9 OR.2.7777 G: (6-4)/6=1/3 squared1/9. OR 0.1111
Xbar=15\sigma =30/9=1.83
4) What is the completion time at 99% confidence level? 99% confidence =(Xbar)+/-3\sigma =153(1.83)9.51.
Similarly for: 95% CI =(Xbar)+/-2\sigma
*
15+3(1.83)20.49
Therefore, we can say with 99% confidence that it will take about 10 and 2012 days to complete the
project.
5) What is the likelihood of this project being completed in more than 16 days?
Z =(1615)/1.83=0.56 then, from ND table.7123.... More than means :1.712328.77%
1.71220.28774. or about 28.77%
*There is about an 29% chance likelihood that the project will be completed in greater than 16 days.
6) Between 14 and 17 days?
Z1=(1415)/1.83=0.550.2912(using table provide)
Z2=(1715)/1.83=1.090.8621
In between means subtract table answers!
0.86210.2912=.570957.09%
*There is about a 57% chance (that the project will take between 14 & 17 days.
i. GRAPH of Network with TIMES See above
SUMMARY:
(You should provide a Summary) All work must be clearly shown!
ii Critical Path: B E G.4+6+5=15
iii. Xbar =15
v. CI:99%[102012].
Highlighted on Network
iv. Sigma =1.83(work provided above)
vi.ND1: (Px>16)=29%. vii.ND2: (P14>x>17)=57%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!