Question: Network Scheduling Data Network Scheduling Data Activity Predecessor ( s ) Duration ( days ) A - - - 5 B A 2 0 C

Network Scheduling Data
Network Scheduling Data
Activity
Predecessor(s)
Duration (days)
A
---
5
B
A
20
C
A
15
D
A
5
E
B, C
60
F
D
15
G
E
20
H
E
15
I
F, G, H
2
Figure 8-6 Network Scheduling Data
Consider the network scheduling data provided in Figure 8-6. Which activities constitute the critical path for this project network?
Group of answer choices
A-B-E-G-I
A-B-E-H-I
A-C-E-H-I
A-D-F-I