Question: Given the information in Table 1, construct a network diagram of the project under normal conditions. Then answer the questions in the Table 2 (next
Given the information in Table 1, construct a network diagram of the project under normal conditions.
Then answer the questions in the Table 2 (next page).
Next, assume that the project manager will receive a bonus of $600 per day for each day that the project duration is reduced. However, the project manager is also responsible for the expediting costs associated with crashing the project. Based on this information, indicate which tasks should be expedited & in which order. Record your answers in Table 3 (next page).
| Activity | Predecessor | Normal Duration | Days Available to Crash | Crash Cost (per day) |
| A | None | 7 | 2 | $ 650 |
| B | A | 3 | 2 | $ 100 |
| C | A | 2 | 2 | $ 300 |
| D | A | 9 | 3 | $ 50 |
| E | B & C | 5 | 1 | $ 300 |
| F | D & E | 7 | 2 | $ 750 |
Draw project network:
Table 2:
| Question | Answer |
| What is the critical path under normal conditions? |
|
| What is the project duration under normal conditions? |
|
Table 3:
| Day Crashed | Task(s) Expedited | Cost of Crashing |
| 1st |
|
|
| 2nd |
|
|
| 3rd |
|
|
| 4th |
|
|
| 5th |
|
|
| 6th |
|
|
| 7th |
|
|
| 8th |
|
|