Question: Given the information in Table 1, construct a network diagram of the project under normal conditions. Then answer the questions in the Table 2 (next

Given the information in Table 1, construct a network diagram of the project under normal conditions.

Then answer the questions in the Table 2 (next page).

Next, assume that the project manager will receive a bonus of $600 per day for each day that the project duration is reduced. However, the project manager is also responsible for the expediting costs associated with crashing the project. Based on this information, indicate which tasks should be expedited & in which order. Record your answers in Table 3 (next page).

Activity

Predecessor

Normal Duration

Days Available to Crash

Crash Cost

(per day)

A

None

7

2

$ 650

B

A

3

2

$ 100

C

A

2

2

$ 300

D

A

9

3

$ 50

E

B & C

5

1

$ 300

F

D & E

7

2

$ 750

Draw project network:

Table 2:

Question

Answer

What is the critical path under normal conditions?

What is the project duration under normal conditions?

Table 3:

Day

Crashed

Task(s)

Expedited

Cost of

Crashing

1st

2nd

3rd

4th

5th

6th

7th

8th

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!