Question: New Microsoft Word Document (2) Review View Help Search . 2 0 | 1 Normal 1 No Spac... Heading 1 Heading 2 Title Subtitle Subtle

New Microsoft Word Document (2) Review View Help Search . 2 0 | 1 Normal 1 No Spac... Heading 1 Heading 2 Title Subtitle Subtle Em.. Emphas. Paragraph Styles The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of actual production are as follows: Standard Costs Foxed overhead (based on 10,000 hours) 3 hours per unit @ $0.77 per hour Variable overhead 3 hours per unit $1.92 per hour Actual Costs Total vanable cost, $17,800 Total fixed cost, $7,900 The amount of the fixed factory overhead volume variance is a.$986 favorable b.$986 unfavorable c.$1,232 unfavorable 0.50