Question: Next question A small software development project at Krishna Dhir's firm has five major activities. The times are vided in the table below: Immediate Predecessor

Next question A small software development

Next question A small software development project at Krishna Dhir's firm has five major activities. The times are vided in the table below: Immediate Predecessor Activity a m b 2 8 B 3 A 4 5 6 7 5 3 9 10 14 2 D E B 3 3 a) The expected completion time for this project is (enter your response as a whole number). b) The project variance value of completion time is (enter your response as a whole number)