Question: Nhen customers order pizza ( task 1 ) , a pizza box is configured ( task 2 ) while thepizza is baked ( task 3
Nhen customers order pizza task a pizza box is configured task while thepizza is baked task Baking the pizza takes the most time task In thisprocess, task and task are completed at the same time in parallelTherefore, Order task and bake task contain slack timemake up the critical pathave configure box task as a dependencyall of the answers are correctnone of the answers are correct