Question: NIE 2. Given the table below: ACTIVITY A B D E F G H a 1 2 1 2 1 1 3 1 3 2

NIE 2. Given the table below: ACTIVITY A B D E F G H a 1 2 1 2 1 1 3 1 3 2 4 4 2 4 2 b 3 4 3 6 7 9 11 3 a. Use the PERT from project management to determine the critical path. (indicate all your calculations clearly) [20] NIE 2. Given the table below: ACTIVITY A B D E F G H a 1 2 1 2 1 1 3 1 3 2 4 4 2 4 2 b 3 4 3 6 7 9 11 3 a. Use the PERT from project management to determine the critical path. (indicate all your calculations clearly) [20]
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
