Question: Nine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, 7 percent; fatigue, 5 percent; delay, 6

Nine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, 7 percent; fatigue, 5 percent; delay, 6 percent. the Work Measurement Excel template to determine the standard time for this operation.
Work
Observation
\table[[Element,1,2,3,4,5,6,7,8,9,Performance Rating],[A,0.09,0.14,0.07,0.05,0.10,0.09,0.15,0.14,0.15,105%