Question: Nine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, six percent; fatigue, six percent; delay, seven

Nine observations from a work measurement study using continuous timing are shown below. Allowances are determined as: personal, six percent; fatigue, six percent; delay, seven percent. Use the Work Measurement Excel template to determine the standard time for this operation.

Work Observation
Element 1 2 3 4 5 6 7 8 9 Performance Rating
A 0.12 0.15 0.09 0.07 0.14 0.12 0.16 0.15 0.16 90%
B 0.25 0.22 0.21 0.22 0.27 0.25 0.27 0.25 0.25 85%
C 0.48 0.50 0.48 0.47 0.49 0.49 0.50 0.48 0.49 100%
D 0.64 0.68 0.65 0.59 0.70 0.68 0.68 0.68 0.72 105%
E 0.73 0.77 0.74 0.68 0.82 0.82 0.76 0.81 0.82 100%
F 1.01 1.05 0.98 0.99 1.10 1.11 1.05 1.08 1.10 85%

Round your answer to two decimal places.

minutes

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!