Question: Nino Spirelli has constructed the following ( partial ) time - phased MPS record:Power Tools ( PT ) has just received an order for 7

Nino Spirelli has constructed the following (partial) time-phased MPS record:Power Tools (PT) has just received an order for 70PT band saws, to be shipped at the beginning of week 9. Information concerning the saw assembly is given here:
\table[[PT Band Saw],[Item,Lead Time (weeks),Components],[Saw,2,A(2**),B,C(3)
\table[[,\table[[On],[hand]],Week],[,1,2,3,4,5,6],[Forecast,20,30,20,30,20,30],[Orders,14,8,6,,,],[\table[[Projected available],[balance]],5,,,,,,],[Available-to-promise,,,,,,],[MPS,50,,50,,50,50]]
a. Complete the record.
b. Are there any problems?
c. What's the earliest Nino can promise an order for 44 units?
d. Assume that an order for 15 is booked for week 4. Assume the order for 44 units in part c is not booked; recompute the record.
 Nino Spirelli has constructed the following (partial) time-phased MPS record:Power Tools

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!