Question: no bookmarked, confident, or note marked Question 5 : Andrew is managing a project by using Microsoft Project. A critical task is out of scope
no bookmarked, confident, or note marked Question 5 : Andrew is managing a project by using Microsoft Project. A critical task is out of scope for the project. The stakeholders advise that the task should be removed from the project but kept in the plan in case the task is needed in the future. He needs to execute a solution to meet the stakeholder's request. What should he do? This type of question contains radio buttons and checkboxes for selection of options. Use Tab for navigation and Enter or space to select the option. option A Select the task and click Inactivate. option B Move the task to the end of the project schedule. option C Delete the task from the schedule. option D Click the Unlink Task button
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts