Question: No. Statement True / False 1 If the cost variance is +$100, the activity is over budget. 2 CPI and SPI are used for trend

No.

Statement

True / False

1

If the cost variance is +$100, the activity is over budget.

2

CPI and SPI are used for trend analysis.

3

If SV = (-$200), the project is over budget.

4

The most challenging part of EVMS is to determine EV or % complete?

5

EAC can be greater or less than BAC.

6

The 50-50 rule is to determine AC.

7

Variances are usually expressed in percent as well as hours or dollars.

8

Scope changes should be paid for out of the management reserve.

9

As you progress through the life cycle phases of a project, the accuracy of the estimates usually improves.

10

The summation of all the PV for each work package should equal BAC.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!