Question: Normal Crash Immediate Normal Crash Activity Time Time Predecessors Cost Cost (Weeks) (Weeks) A -- 4 3 $1500 $1575 B -- 2 1 $2100 $3600

Normal Crash Immediate Normal Crash Activity Time

Normal Crash Immediate Normal Crash Activity Time Time Predecessors Cost Cost (Weeks) (Weeks) A -- 4 3 $1500 $1575 B -- 2 1 $2100 $3600 -- 3 $1700 $1700 3 8 D A 8 4 $2200 $2700 E B 6 3 $1500 $1800 F 3 2 $1100 $1300 G D, E 4 2 $1400 $1500 04 A (4) 412 D (8) 1216 G (4) 010 START 02 B (2) 28 E (6) 116 16 END 03 C (3) 316 F (3) What is the minimum additional cost to reduce the project completion time to 9 weeks (first compute the critical path and then determine the sequence of activities to crash to bring reduce project completion time)