Question: What is the minimum additional cost to reduce the project completion to 9 weeks ? Development of an update of a particular software product is

What is the minimum additional cost to reduce the project completion to 9 weeks ?
Development of an update of a particular software product is being considered by a software house. Information on the activities necessary for the completion of this project is provided in the following table: Normal Crash Immediate Normal Crash Activity Time Time Predecessors Cost Cost (Weeks) (Weeks) A -- 4 3 $1500 $1800 B -- 2 1 $2000 $2500 -- 3 3 $1700 $1700 D A 8 4 $2300 $2600 E B 6 3 $1600 $1840 F. C C 3 2 $1200 $1300 G D, E 4 2 $1200 $1600 04 A (4) 412 D (8) 1216 G (4) 010 START 02 B (2) 28 E (6) 16 16 END 013 C (3) 316 F (3) 1Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts