Question: NORMAL CRASHED Activity NORMAL Duration ( weeks ) NORMAL Cost ( $ ) CRASHED Duration ( weeks ) CRASHED Cost ( $ ) Maximum Crashed

NORMAL CRASHED
Activity NORMAL Duration (weeks) NORMAL Cost ($) CRASHED
Duration
(weeks) CRASHED
Cost ($) Maximum Crashed Cost ($) Number of Potential Crash Du-rations (weeks) Crash Cost per Pe-riod ($/week)
A 522,000323,9001,9002950
B 830,000440,00010,00042,500
C 526,000327,1001,1002550
D 848,000549,5001,5003500
E 756,000559,0003,00021,500
F 630,000530,7007001700
G 880,000781,2501,25011,250
H 516,000323,0007,00023,500
The following Project Network Paths have been identified:
Path 1: B D G H =8+8+8+5=29 weeks
Path 2: A C E G H =5+5+7+8+5=30 weeks
Path 3: A C F H =5+5+6+5=21 weeks how do you crash the project from 30 weeks to 26 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!