Question: Norton Industries is installing a new computer system. The activities, the activity times, and the project network are as follows. The critical path calculation shows

Norton Industries is installing a new computer system. The activities, the activity times, and the project network are as follows.
The critical path calculation shows B-D-E-F-H is the critical path, and the expected project completion time is 21 weeks. After viewing this information, management requested overtime be used to
complete the project in 16 weeks. Thus, crashing of the project is necessary. The following information is relevant.
(a) Formulate a linear programming model that can be used to make the crashing decisions for this project. (The objective function should be the additional cost of crashing. Let xi= the finish time
for activity i and yi= the amount of time activity i is crashed where i=A,B,C,D,E,F,G, and H.)
Min|??
s.t.
constraint A
constraint B
C depends on A
D depends on C
D depends on B
E depends on D
F depends on E
G depends on C
G depends on B
H depends on G
H depends on F
finish time for H
maximum crashing for A
maximum crashing for B
maximum crashing for C
maximum crashing for D
maximum crashing for E
maximum crashing for F
maximum crashing for G
 Norton Industries is installing a new computer system. The activities, the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!