Question: Norton Industries is installing a new computer system. The activities, the activity times, and the project network are as follows. The critical path calculation shows
Norton Industries is installing a new computer system. The activities, the activity times, and the project network are as follows.
The critical path calculation shows BDEFH is the critical path, and the expected project completion time is weeks. After viewing this information, management requested overtime be used to
complete the project in weeks. Thus, crashing of the project is necessary. The following information is relevant.
a Formulate a linear programming model that can be used to make the crashing decisions for this project. The objective function should be the additional cost of crashing. Let the finish time
for activity i and the amount of time activity is crashed where and H
Min
st
constraint A
constraint B
depends on
D depends on
D depends on
E depends on
depends on
depends on
depends on
depends on
depends on
finish time for
maximum crashing for
maximum crashing for
maximum crashing for
maximum crashing for
maximum crashing for
maximum crashing for
maximum crashing for
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock