Question: Note: Answer (4) questions only from the following: Q2: From the following data table, create a business network, then find the critical path, select the

Note: Answer (4) questions only from the following: Q2: From the following data table, create a business network, then find the critical path, select the critical activities, find the early starting and late starting Activity Preceding activity Time A 10 B A 11 B D B E A F C D G F H E 1 G H 5 4 12 3 7 11 6 (20 marks)