Question: Note: Explain your solutons step by step. Write your solutions understandble and eligible, thanks. A maintenance department has 6 jobs to be processed. All the

Note: Explain your solutons step by step. Write your solutions understandble and eligible, thanks.
A maintenance department has 6 jobs to be processed. All the time units are in terms of days. Processing Due date time Time since job arrived A 8 5 12 B 7 7 18 C 6 8 6 D 4 3 10 E 2 9 22 F 1 12 17 According to the given information and SPT rule, what is the average flow time? a. between 16 and 18 days mo b. Fever than 16 days c. between 19 and 20 days d. More than 23 days e. between 21 and 22 daysStep by Step Solution