Question: Operations Management 5. Consider the following project. Task Immediate Predecessors Optimistic Most probable Pessimistic Crash Time Normal Cost Crash Cost A - 4 6 8

Operations Management

5. Consider the following project.

Task

Immediate Predecessors

Optimistic

Most probable

Pessimistic

Crash

Time

Normal

Cost

Crash

Cost

A

-

4

6

8

4

1000

1900

B

-

6

8

16

7

1000

1800

C

A, B

2

4

6

2

1500

2700

D

C

8

10

24

8

2000

3200

E

C

7

10

13

7

5000

8000

F

E

4

6

8

4

3000

4100

G

C

4

6

20

5

8000

10250

H

D, F, G

4

6

8

4

5000

6400

I

D, F

4

6

14

4

10000

12400

J

H

3

4

5

3

4000

4400

K

I, J

2

4

6

3

5000

5500

  1. Draw a project network
  2. Find the critical path and expected project completion time.
  3. Assuming that management desire a 37 weeks project completion time. What activity should be crashed?
  4. Activity schedule table after crashing.
  5. Find total project cost after crashing.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!