Question: Note: Please provide answer as soon as possible Question 6 a. Describe some of the limitations of using the Johnson's rule for sequencing. [2] b.

Note: Please provide answer as soon as possible

Note: Please provide answer as soon as possible

Question 6 a. Describe some of the limitations of using the Johnson's rule for sequencing. [2] b. A repair shop has 5 tasks that need to be performed and is listed chronologically as they arrived. Compare the scheduling criterion using first come first serve (FCFS), shortest processing time (SPT) and earliest deadline date (EDD). [8] Process time Due Date Task V W X Y Z 4 10 6 12 22 10 33 27 8