Question: Note that there is no separate process in the Project Cost Estimation knowledge area to develop a cost management plan. A particular project in the
Note that there is no separate process in the Project Cost Estimation knowledge area to develop a cost management plan. A particular project in the domain of civil construction requires that every on-site worker be insured. Which of the following inputs BEST conveys this requirement to the Cost Estimation process so that the insurance cost is estimated and subsequently budgeted?
A-Enterprise Environmental Factor
B-Organizational Process Assets
C-Project Scope Statement
D-Project Management Plan