Question: Note - The duration are in Weeks. Draw a corresponding AON network. Compute ES and EF for each activity. Compute LS and LF for each

Note - The duration are in Weeks.
Draw a corresponding AON network. Compute ES and EF for each activity. Compute LS and LF for each activity. Find the critical path. Determine the total slack and free slack. Activity Predecessors Duration A . A B. C D E F G H J K M N C B,D E C B,D.G anon + + momo 10 G,K HM 6Step by Step Solution