Question: Note: You can right-click the image then open in a new tab to better see the problem A production process at Kenneth Day Manufacturing is

Note: You can right-click the image then open in a new tab to better see the problem
A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). 5 units/hr 2.5 units/hr Assembly 0.8 units/hr Sawing Sanding Welding 5 units/hr Assembly 0.8 units/hr Drilling 2.1 units/hr Assembly 0.8 units/hr a) is the bottleneck. Drilling Sanding Sawing Welding Clic iswer(s) and then click Check Answer. ? Assembly