Question: Note: You will find the Example videos in the module very helpful in answering these questions. Please type or write only a number or text
Note: You will find the Example videos in the module very helpful in answering these questions. Please type or write only a number or text in the text box provided.
Use the ActivityonArrow AOA diagram on the following page to determine the following each number is the number of hours for the task.
table How many different paths are there through the network? pointsWhat is the number of the last node in the network? pointsWhat is the difference in hours taken for the two paths when they,connect at node pointsWhat is the ditference in houss taken for the two paths when they,What is the expected duration of the entire project? pointsWhat pointsWhat is the critical path Separate each node with a dosh points
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock