Question: Note: You will find the Example videos in the module very helpful in answering these questions. Please type or write only a number or text
Note: You will find the Example videos in the module very helpful in answering these questions. Please type or write only a number or text in the text box provided.
Use the ActivityonArrow AOA diagram on the following page to determine the following each number is the number of hours for the task.
table How many different paths are there through the network? pointsb What is the number of the last node in the network? pointsc What is the difference in hours taken for the two paths when they connect at node pointsd What is the difference in hours taken for the two paths when they connect at node pointse What is the expected duration of the entire project? pointsf What is the critical path? Separate each node with a dash pointsg Which is the longest path? Separate each node with a dash points
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock