Question: Now take another look at it , and how it mixes with the last path. It includes activity H , which was also in the

Now take another look at it, and how it mixes with the
last path. It includes activity H, which was also in the
last path. H will have a different ES depending on which
path you use! So which predecessor do you use - E or G?
The idea here is that you use the predecessor with the
larger EF value when you calculate the ES for activity H
(because you want the latest possible start date).
 Now take another look at it, and how it mixes with